ALDI STORE – RODEZ
Construction of a sales area ALDI.
LOTS : – Earthworks
– Structural work
– Interior masonry and plastering
– Facades
– Infrastructures
YEAR : 2017
ALDI STORE – RODEZ
Construction of a sales area ALDI.
LOTS : – Earthworks
– Structural work
– Interior masonry and plastering
– Facades
– Infrastructures
YEAR : 2017
New Wastewater Treatment Plant of Cagnes-sur-Mer – Digestion Zone
Treatment of wastewater for 160,000 inhabitants (Cagnes-sur-Mer, La Colle-sur-Loup, Villeneuve Loubet, and St-Paul de-Vence municipalities). It is the first positive energy wastewater treatment plant in France, producing more energy than it consumes, thus justifying a BREAM VERY GOOD certification.
LOCATION : Cagnes-sur-Mer
CLIENT : SYMISCA
GENERAL : SPADA Construction
LOTS : – Reinforced Concrete Structure
– Decorative concrete walls (architectural concrete)
– Glass Facades
ANOS : 2018-2019
Operational Center “FORCE 06” (Levens)
DESCRIPTION : One-story building consisting of offices, a garage, and a mechanical workshop
LOCATION : Levens
CLIENT : Alpes Maritimes Department
ARCHITECTS : COMBAS ARCHITECTES
LOTS : – Special foundations
– Structural work
– Reinforced concrete walls / Stone
– Masonry and plastering
– Metal framework
– Aluminium Frames
– Glass facades
YEARS : 2020 – 2021
TGV Maintenance Center Level 2 (Nice)
LOCATION : Nice
PROJECT MANAGEMENT: SNCF
LOTS : – Earthworks
– Infrastructures
– Infrastructures and bituminous paving
– Structural work
– Reinforced concrete structure
– Metal framework (EME Singular)
YEARS : 2013-2014
O’PARK – MARSEILLE
Construction of a building of 144 apartments
PROJECT MANAGEMENT : ICADE PROMOTION
GENERAL CONTRACTOR : TRAVAUX DU MIDI (Groupe VINCI)
LOTS : – Steel structure
YEAR : 2017
Construction of a source station
225/20 kV peri-urban source substation consisting of a building for the 225 kV PSEM (ground floor + HV cable gallery), a reinforced concrete building with 3 225/20 kV TR boxes (R+3 with a basement level), a building for the ERDF premises (R+1 with a basement level)
LOCATION: Aix-en-Provence
PROJECT MANAGEMENT: ERDF
ARCHITECT: José Morales Architect
LOTS: – Civil engineering
– Structural work
– Masonry
YEAR: 2013
PROJECT MANAGEMENT: Vallauris Golfe-Juan City Hall
ARCHITECTS : MIND Architecture
DESCRIPTION: Structural work, external aluminium joinery (EME Singular), Occultations, wood cladding, Decking
YEARS: 2021
Upgrading of a waste disposal center
PROJECT MANAGEMENT: UNIVALOM
LOTS : – Earth works
– Infrastructures
– Paving (concrete and bituminous)
– Retaining Walls
– Rainwater Retention Tank
YEARS : 2019
Renovation of the workshops of the Palais de la Découverte
PROJECT MANAGEMENT: OPPIC
LOTS : – Structural works
– Metal Framework
– Masonry
– Floor covering
– False ceilings
– Painting
YEAR : 2016
WASTEWATER TREATMENT PLANT – METAL FRAMEWORK
LOCATION: Cagnes-sur-Mer
PROJECT MANAGEMENT: SYMISCA
GENERAL CONTRACTOR: SPADA Construction
LOTS : – Metal framework
– Aluminium Frames
– Glass facade (ABB Construction / EME Singular)
YEARS : 2019-2020